CONDOR-FM Release 2026.2.0 Sprint Retrospective
A detailed analysis of software release 2026.2.0 including timeline variations, bottleneck analysis, and action items for process improvement.
Retrospective : SW
Release
CONDOR-FM-rel2026.2.0
Version 2026.2.0
mynaric.com
17.02.2026
mynaric
Planned vs Actual Timeline
mynaric.com
17.02.2026
mynaric
Flow & Bottlenecks Analysis
April 29, 2026
Total Issues
35 Issues
Stories (SW/TC)
21
Bugs
14
Based on average of 12 critical tickets
Time Spent by Status
In Progress
61
61 days
In Review
41
41 days
⚠ Highest Time Spent
Acceptance
46
46 days
Major bottleneck
observed in
"In Progress"
phase, indicating longer development cycles or blocked work.
Impact: +7 days delay
mynaric.com
Version 2026.2.0
mynaric
Progress of Previous Action Items
Tracking implementation status of top-voted retrospective action items
Last Updated
April 29, 2026
Collection Process
Retrospective Board
Captured all suggestions
Voting & Prioritization
Developers voted on items
Jira Epic Created
Tracked as work items
Retrospective Epic
CONDORMK3-FM-rel2025.2.0
28
14
3
Top 3 Voted Action Items
1. Establish Dedicated Release Testing Strategy
Including hiring needs for test engineers
12 votes
In Progress
65
2. Increase Test Automation & Reduce Manual Work
Automated testing framework implementation
10 votes
In Progress
45
3. Follow-Up Mechanism for Previous Retro Action Items
Tracking implementation status
8 votes
Done
100
14
8
6
Last updated: 2 hours ago
mynaric.com | Version 2026.2.0
Page 4 of 5
mynaric
- sprint-retrospective
- software-engineering
- project-management
- agile-metrics
- release-management
- software-testing