# CONDOR-FM Release 2026.2.0 Sprint Retrospective
> A detailed analysis of software release 2026.2.0 including timeline variations, bottleneck analysis, and action items for process improvement.

Tags: sprint-retrospective, software-engineering, project-management, agile-metrics, release-management, software-testing
## CONDOR-FM Release 2026.2.0 Retrospective
* **Release Version:** 2026.2.0
* **Date:** February 17, 2026

## Planned vs Actual Timeline
* **Observation:** The project experienced a +7 day delay compared to the original schedule.
* **Key Milestones:** Analysis covers Dev Start, Dev Complete, Testing, and Final Release.

## Flow & Bottlenecks Analysis
* **Statistics:** 35 total issues (21 Stories, 14 Bugs).
* **Wait Times:**
    * In Progress: 61 days (Major bottleneck identified).
    * In Review: 41 days.
    * Acceptance: 46 days.
* **Impact:** Development cycles/blocked work led to a 7-day variation in the final deadline.

## Progress of Previous Action Items
* **Top Priorities:**
    * 1. Establish Dedicated Release Testing Strategy (65% complete).
    * 2. Increase Test Automation & Reduce Manual Work (45% complete).
    * 3. Follow-Up Mechanism for Previous Retro Items (100% complete).
* **Tracking:** Managed via Jira Epic CONDORMK3-FM-rel2025.2.0 with a 28% overall completion rate for those specific action items.
---