Rove Home Project: Weekly Construction Progress Update 2026
Explore the January 2026 progress report for Rove Home, covering structural works, financial overviews, facade status, and HSE performance indicators.
Weekly Progress Update
Construction Management Report | Rove Home Project
January 2026
Executive Summary
Structural crown works are 95% complete, finalizing steel reinforcement.
Facade installation on upper levels has commenced ahead of schedule.
Top-out ceremony scheduled for next week pending final inspection.
Podium & Landscape Progress
Swimming pool tiling reaches 80% completion; waterproofing passed inspection.
Hard-scaping of the main deck and walkway areas initiated.
Planting soil delivery scheduled for Thursday; soft-scaping to follow.
Construction Phases: Plan vs. Actual
Financial Overview (Q1 2026)
$14.5M
Expenditure to Date
2.1%
Under Budget Variance
Exterior & Facade Status
Primary glazing is complete up to Floor 30. Current focus is on balcony balustrades and aesthetic cladding panels.
Entrance & Drop-off Area
Driveway paving pattern approval received.|Canopy structure steel erection 100% complete.|Lighting fixtures installation in progress.
HSE Performance Indicators
0 LTI
Lost Time Injuries this Month
Two-Week Lookahead
Completion of Level 45 slab casting.
Initiation of elevator cabin installation in Shaft B.
Testing and Commissioning of podium water features.
Final selection of lobby marble finishes.
Thank You
Project Management Team