# Rove Home Project: Weekly Construction Progress Update 2026
> Explore the January 2026 progress report for Rove Home, covering structural works, financial overviews, facade status, and HSE performance indicators.

Tags: construction-report, project-management, real-estate-development, weekly-update, site-progress, construction-management
## Weekly Progress Update - Rove Home Project
- **Project Date:** January 2026
- **Executive Summary:** Structural crown works are 95% complete; facade installation on upper levels has commenced ahead of schedule. Top-out ceremony is imminent.

## Podium & Landscape Progress
- Swimming pool tiling is 80% complete.
- Waterproofing has passed inspection.
- Hard-scaping initiated; soft-scaping to follow soil delivery.

## Construction Phases: Plan vs. Actual
- **Substructure:** 100% (Planned) vs 100% (Actual)
- **Superstructure:** 95% (Planned) vs 98% (Actual)
- **Facade:** 70% (Planned) vs 75% (Actual)
- **MEP:** 60% (Planned) vs 55% (Actual)
- **Interiors:** 40% (Planned) vs 35% (Actual)

## Financial Overview (Q1 2026)
- **Total Budget:** $20.0M
- **Expenditure to Date:** $14.5M
- **Budget Variance:** 2.1% under budget.

## Exterior & Entrance Status
- Primary glazing complete up to Floor 30.
- Focus shifted to balcony balustrades and aesthetic cladding.
- Canopy structure steel erection is 100% complete at the entrance.

## HSE Performance (Health, Safety, & Environment)
- **Lost Time Injuries (LTI):** 0 this month.
- **Manpower:** 420 for Civil Works; 250 for MEP Works.
- **Safe Manhours:** 120k (Civil); 85k (MEP).

## Two-Week Lookahead
- Completion of Level 45 slab casting.
- Initiation of elevator installation in Shaft B.
- Testing of podium water features.
- Final selection of lobby marble finishes.
---