Barjeel Substation JVC Energization Report | January 2026
Official energization report for the 132/11 KV Barjeel Substation in Dubai. Technical specs, milestones, and safety results from DEWA and Danway.
Project Energization Report
132/11 KV Barjeel Substation JVC | Official Results
January 2026
Executive Summary: Successful Energization
Project 132/11 KV Barjeel Substation in JVC successfully energized on 22.01.2026.
Delivered in partnership with Dubai Holding, DEWA, and Danway E&M Engineering.
Asset is now fully operational and integrated into the power grid.
Key Project Stakeholders
Dubai Holding & DEWA (Dubai Electricity & Water Authority)
Danway Electrical & Mechanical Engineering L.L.C.
AFRY
Project Status Comparison
Pre-Energization (Before Jan 22)
Installation Phase Cold Commissioning Only Safety Perimeter Active No Grid Load
Post-Energization (Result)
Operational Phase Live 132kV Voltage Grid Synchronization Complete Supporting JVC Infrastructure
Technical Specifications: Barjeel Substation
Primary Voltage: 132 KV
Secondary Voltage: 11 KV
Location: Jumeirah Village Circle (JVC)
Project Milestones to Energization
Civil Construction
Equipment Installation
Cold Commissioning
DEWA Inspection
ENERGIZATION (Jan 22, 2026)
Operational Impact & Benefits
Enhanced Power Reliability for JVC District
Increased Grid Capacity for Future Developments
Seamless Integration with DEWA Network
Safety & Compliance Results
From the construction phase until energization day, Danway operated with full safety compliance, successfully achieving 781,230 Safe Man-Hours without any lost time incidents.
Next Steps: Post-Energization
24-Hour Soak Test Completion
Load Gradual Increase
Final Handover Documentation
Thank You
Danway E&M Engineering | Dubai Holding | DEWA