# Barjeel Substation JVC Energization Report | January 2026
> Official energization report for the 132/11 KV Barjeel Substation in Dubai. Technical specs, milestones, and safety results from DEWA and Danway.

Tags: dewa, substation, energization, dubai-holding, electrical-engineering, jvc, power-grid, utility-project
## Project Energization Report
* **Project:** 132/11 KV Barjeel Substation JVC
* **Date:** January 2026
* **Partners:** Dubai Holding, DEWA, Danway E&M Engineering, and AFRY.

## Executive Summary
* Successfully energized on January 22, 2026.
* Asset is fully operational and integrated into the power grid.

## Project Status Comparison
* **Pre-Energization:** Cold commissioning, safety perimeter active, no grid load.
* **Post-Energization:** Live 132kV voltage, grid synchronization complete, supporting JVC infrastructure.

## Technical Specifications
* **Primary Voltage:** 132 KV
* **Secondary Voltage:** 11 KV
* **Location:** Jumeirah Village Circle (JVC)

## Project Milestones
* Civil Construction
* Equipment Installation
* Cold Commissioning
* DEWA Inspection
* **ENERGIZATION:** Jan 22, 2026

## Safety & Compliance
* Achieved **781,230 Safe Man-Hours** without any lost time incidents (LTI).

## Operational Impact
* Enhanced power reliability for JVC District.
* Increased grid capacity for future developments.
* Seamless integration with the DEWA network.

## Next Steps
* 24-Hour soak test completion.
* Gradual increase of load.
* Final handover documentation.
---